Slurry Sealing on Various City Streets

Project Type:
Street
Project Status: 
Approved and Under Construction

Starting on Monday, June 17th, the City's contractor will begin removing striping from various city streets to prepare for them to be slurry sealed on Wednesday, June 19th and Thursday, June 20th. Below is the list and locations of where work is being performed:

Wednesday, June 19    
Street From To
Annis Rd San Bruno Ave Humboldt Rd
WB Main St Linda Vista  Bayshore
Monterey St San Bruno Ave Alvarado St
Sierra Point Rd Place Wy San Benito Rd
San Francisco Alvarado St Santa Clara
San Francisco Visitacion Ave Alvarado St
San Mateo Rd Kings Rd Humboldt Rd
     
Thursday, June 20    
Street From To
EB Main St Linda Vista  Bayshore
San Benito Rd Visitacion Ave Sierra Point Rd
San Benito Rd Sierra Point Rd Visitacion Ave
Humboldt Rd Dead End Sierra Point Rd
Klamath St Sierra Point Rd Visitacion Ave
Thomas Ave San Bruno Ave Dead End
Mariposa St Visitacion Ave San Bruno

Please note: No Parking signs are being placed on the above streets; please do not park on the affected portion of the street during construction hours of 8 AM - 5 PM. The signboards have also been updated to reflect this work. We thank you for your patience and hope you enjoy the newly-paved streets!

San Francisco St.